Construction Update: Merion Cricket Club

04.11.2018

The construction and renovation of Merion Cricket Club’s locker room and squash court facility continues to make progress as the project moves quickly toward completion.

Locker installation is complete on the third floor in the newly-renovated Men’s Locker Room, which will also include a sauna and steam room. A new elevator was also installed.

The second floor of the facility is undergoing renovations to create a new men’s lounge and fitness studio. Currently, the sports floor and interior trims are underway. A second fitness center and attached studio will be built on the first floor, along with a reception area.

The largest transformation is occurring in the newly reconfigured Squash Courts. The courts are complete and awaiting installation of the new wood flooring.

WS Cumby is currently providing Construction Management services for Phase 1 of the Campus Master Plan for Merion Cricket Club in Haverford, Pennsylvania. Phase 1 focuses on the renovation and restoration of existing portions of Merion Cricket Club’s historic campus.

  • Share

04.04.2018

W.S. Cumby Breaks Ground at the Institute for Advanced Study

W.S. Cumby Construction attended a groundbreaking ceremony at The Institute for Advanced Study in Princeton, NJ for the Rubenstein Commons, a new $20 million building that will support community ...

03.28.2018

W.S. Cumby Breaks Ground at The Benchmark School

W.S. Cumby Construction, along with Cicada Architecture and Northstar Owner’s Representation, recently broke ground at The Benchmark School in Media, Pennsylvania for the school’s new ...